Leave pay
Rm |
Incentive
bonus
Rm |
Rehabilitation
provision*
Rm |
Total
Rm |
| Balance as at 30 June 2024 |
|
51 |
104 |
23 |
178 |
| Provision raised/transferred |
|
24 |
194 |
13 |
231 |
| Provision utilised |
|
(25) |
(202) |
– |
(227) |
| Balance as at 30 June 2025 |
|
50 |
96 |
36 |
182 |
| Provision raised/transferred |
|
40 |
164 |
2 |
206 |
| Provision utilised |
|
(42) |
(170) |
– |
(212) |
| Balance as at 30 June 2026 |
90 |
38 |
|
|
|
|
|
|
| * |
Rehabilitation provision is non-current. |
Leave pay is provided on accumulated leave balances at year-end based on the employees’ cost to company.
Provision for incentive bonus is expected to be realised when bonuses are paid in FY2026 and is based on terms as dictated in employment contracts (subject to the final approval from management).
The rehabilitation provision represents the best estimate of the discounted future cost of either restoring quarries to their original state or eliminating adverse environmental impacts to an acceptable level over the long term.
|